Building regulations
Private building control in London
You can choose who checks your building work: your council's building control team or a private firm. Private firms must now be registered with the Building Safety Regulator. We prepare the drawings and coordinate the application with whichever you choose. Fixed quote after a free constraints check.
Fixed quote after a free constraints check
- MCIAT chartered
- £2m PI insured
- LABC Partnered
- Fixed fees, VAT included
Request a fixed quote

Council or private building control: the choice
Building control is the independent check that building work meets the Building Regulations. Two kinds of body can do it. Your local authority has a building control team for its area. A private firm can do the same job anywhere it is registered to work.
The legal tests are identical, so neither is a soft option. What differs is service: how quickly they visit, how they communicate, how they charge and how flexible they are about inspection times. Some owners also like to keep a single firm across several projects.
We do not act as a building control body ourselves. We coordinate the application, so the drawings and notices go to whichever body you appoint.
Ask each body what it will inspect and when. Visits normally follow the stages of the work: foundations, drains, structure, insulation and completion. Agreeing the sequence early stops a trench being backfilled before it is seen.

The registration rule that now applies
Private building control firms must be registered building control approvers with the Building Safety Regulator. That requirement is in force now. Before it, the equivalent was an approved inspector.
The rule has teeth. Operating as an approved inspector without registering is a criminal offence. For you, the practical point is simple: before you appoint a private firm, check that it is on the regulator's register of approvers.
We will point you to the register and check the firm's status when we coordinate your application.
Ask for the firm's registration details and look them up yourself; the regulator keeps the register of approvers.
How charges work
Local authority charges are set by each council's own charging scheme, which is designed to recover the cost of the service. They differ from borough to borough, and the council publishes its scheme.
Private firms set their own fees. Compare like with like: ask what is included, how many inspections, and whether a completion certificate is part of the price. A low quote that leaves out visits can end up costing more.
The building control fee is separate from ours. We can describe what the examiner will need to see, but we do not set or take their fee.
Check what happens if the project changes. A change of scope, such as adding a loft to an extension, can alter the fee, so ask how a revised design is charged before you sign.
Timing and the full plans decision
Whichever body you choose, the same rule applies to a full plans application: the building control body must decide within a set statutory period, or longer if agreed in writing. The figure is in the table.
Speed in practice depends on how complete your drawings are. An examiner who finds gaps will issue queries, and each round adds time. That is why we prepare a set that already carries structure, insulation, fire and drainage information. See our building regulations drawings page for what the set contains.
Do not treat the statutory period as a promise of approval. It is the time allowed to give an answer.
What happens if rules are broken
Contravening the Building Regulations is an offence. Under the Building Act 1984, as changed by the Building Safety Act 2022, a conviction on indictment can bring a fine or up to two years' imprisonment. Work that ignores the regulations carries that risk.
The more common consequence is practical. Without a completion certificate, a buyer's solicitor will raise it, and a lender may hold back. Choosing a registered body and keeping to the notice sequence avoids all of that.
How we coordinate the application
We prepare the technical drawings, submit the application to your chosen body and respond to the examiner's questions. We also prepare the commencement and completion notices, so the sequence of visits is not missed.
Where the work needs engineering, we coordinate with structural calculations. Where the design needs detailed specification, our construction drawings page describes the full set. A reviewer who is not the drafter checks the submission, and we amend the drawings free of charge if the examiner raises queries.
The national rules in figures
| Measure | Value | Period | Source |
|---|---|---|---|
| GOV.UK Registered building control approvers | Private building control firms must be registered building control approvers (RBCAs) with the Building Safety Regulator from 6 Apr 2024 | — | gov.uk |
| GOV.UK Registered building control approvers | Operating as an approved inspector after 6 Apr 2024 without registering is a criminal offence | — | gov.uk |
| Building (Local Authority Charges) Regulations 2010 reg 7 | Local authority building control charges are set by each council's charging scheme to recover the cost of the service | — | legislation.gov.uk |
| Building Regulations 2010 reg 14A(6) | Building control body must decide a full plans application within 5 weeks, or longer if agreed in writing | — | legislation.gov.uk |
| Building Act 1984 s35(4), substituted by Building Safety Act 2022 s39 | Contravening building regulations: on indictment up to 2 years' imprisonment or a fine (or both) | — | legislation.gov.uk |
A blank value means the figure has not been published, not that there are none. Check your own address with the council.
Building regulations, layer by layer
The Approved Documents that shape most house projects, from structure to the application itself.
- A · Part A: structure
- Approved Document A: Structure, 2004 edition incorporating 2004, 2010 and 2013 amendments
- B · Part B: fire safety
- All dwellings: fire detection and alarm system minimum Grade D2 Category LD3 (BS 5839-6), mains-operated smoke alarms to BS EN 14604
- C · Part L: insulation
- New elements in existing dwellings, limiting U-values W/(m²·K): roof 0.15, wall 0.18, floor 0.18, windows 1.4 (or WER Band B), doors 1.4
- D · Part K: stairs
- 2.0 m clear headroom over stairs
- E · Full plans application
- Building control body must decide a full plans application within 5 weeks, or longer if agreed in writing
What you receive


Questions
Can I use a private firm instead of the council?
Yes. You can appoint either your local authority's building control team or a registered private firm. The legal tests are the same.
Do private building control firms have to be registered?
Yes. They must be registered building control approvers with the Building Safety Regulator, and operating without registration is a criminal offence.
How are council building control charges set?
Each council sets them in its own charging scheme, designed to recover the cost of the service.
Are you a building control body?
No. We prepare the drawings and coordinate the application with whichever body you appoint.
How long does a full plans decision take?
The building control body must decide within a statutory period, or longer if agreed in writing. No date can be promised.
Sources and dates
- gov.uk, retrieved
- legislation.gov.uk, retrieved
- legislation.gov.uk, retrieved
- legislation.gov.uk, retrieved
- gov.uk, retrieved
- gov.uk, retrieved
- gov.uk, retrieved
- gov.uk, retrieved
- Contains public sector information licensed under the Open Government Licence v3.0.
- Contains OS data © Crown copyright and database right 2026.
- Contains HM Land Registry data © Crown copyright and database right 2026. This data is licensed under the Open Government Licence v3.0.
- Contains Historic England data © Historic England 2026. Contains Ordnance Survey data © Crown copyright and database right 2026.

Tell us about your property.
We check the constraints, then send a fixed fee. Messages before 3pm get a reply the same working day.